Tri-State and Xcel need three separate approvals from federal, state and county governments before they can construct their massive, unnecessary transmission line. Without approval from all three, their project cannot be built.
These processes can be long and drawn out. As a result, it’s difficult to determine when and how you can and should participate in them. Below is a brief overview of each process and the key opportunities for you to influence them.
Federal Approval (2009 to 2012 or later)
The Rural Utilities Service (RUS) oversees an Environmental Impact Statement (EIS) process. The EIS identifies the proposed project’s impacts and assesses whether reasonable mitigation measures can be taken or if there are less-impactful ways to accomplish the purpose and need of the project.
Key Opportunities for Input
State Approval (2009 to mid/late 2011)
The Colorado Public Utilities Commission (PUC) oversees a Certificate of Public Convenience and Necessity process to assess whether there is a need for the line. The PUC’s initial decision recommends granting the CPCN. A final decision on the CPCN could come at any time, but after more than two years the decision is still not issued. Separate from the CPCN, there are a number of other PUC proceedings, including one in which Xcel is slowly revealing that it has no plans to build more solar generation in the San Luis Valley.
Key Opportunities for Input
The PUC conducted hearings to accept testimony in 2010. At this point in the process, there are no additional opportunities for input.
County Approvals (Could begin in 2011 or 2012)
Every county that the transmission line crosses will oversee a decision process related to whether or not they will allow the transmission line to be built in their county. Each county has their own approval process. At this point, it’s unclear when the utilities will begin the county-approval processes.
Key Opportunities for Input